ALRAR: SEPARATION AND BOOSTING PLANT




Algeria

ACTIVITIES

Construction
Plant

The plant takes the fluids from the existing gathering system and boosts their pressure at the inlet of the existing gas and liquid processing facilities.

The plant has 8 compressors and is one of the biggest stations we have ever built. This infrastructure compresses gas from the zone of Alrar so it can be used commercially on the domestic market right away.

The site is located in the desert 1,500 km south of the capital, Algiers, 120 km north of In Amenas and 4 km west of the Libyan border.

SCOPE OF WORK

The contract includes engineering, procurement and construction of gas and gas-condensate separation and compression facilities. Trunkline and flowline work are also included.

Project highlights

Civil and Mechanical Works

Cutting

(m³)

211,000
 

Piping

(id)

113,500

Filling

(m³)

235,000
 

Steel Structure

(tonnes)

3,000
 

Concrete

(m³)

21,500
 

Equipment

(tonnes)

5,900

 

The plant mainly consists of:

 

  • Slug catcher
  • Low-pressure stage compression with 3+1 gas turbine driven compressors
  • High-pressure stage compression with 3+1 gas turbine driven compressors

 

  • Liquid handling facilities
  • Produced water handling and treatment
  • All required utilities, as the plant will be stand-alone

CAREERS

Working at Bonatti means becoming part of dynamic team committed to achieving challenging objectives in international and multicultural contexts.

JOIN US FOLLOW US ON LINKEDIN

REQUEST INFORMATION

Contact us for any commercial and procurement request.

CONTACT US

BECOME A SUPPLIER

Quality, environment and safety starts with the procurement process.

FIND OUT MORE

We use cookies to ensure you get the best experience on our website. More information.